PRHS Expansion Update

Project Time-Line

Week of Nov. 22 & Nov. 29, 2010

  • Construction Vehicles to Move In
  • Temporary Fencing Posted
  • Construction Trailer in Place
  • Access Road Behind High School Closed to Walkers, Joggers & Vehicles
  • Ground to be Broken
December 2010
  • Excavating Begins

The Pine-Richland High Expansion project continues to move forward. You can expect to see construction vehicles moving onto the property at 702 Warrendale Road. Traffic flow should be relatively smooth. However, the access road behind the high school will be closed to the public and only available to construction vehicles. The administration parking area will be restricted as well.

The PR School Board awarded $26.8 million in contracts to nine different companies at its special meeting on Oct. 19.

Total cost of the project will be about $32 million.  The district named Kusevich Construction of Etna as the general construction.
Click here for the bid list.   Groundbr
eaking is expected to get underway late October or early November